Sourcing

Make vs Buy Decision

Compare fully loaded make cost, including constraint opportunity cost, against a supplier buy price, with a separate switching-cost payback check.

Lean buy$34 / unit to make
Full make cost$34
Buy price$30
Annual cost delta$20,000
Constraint hours freed3,750

Sensitivity to constraint value

ScenarioFull make costDelta vs buyStrategy
Constraint value -20%$31.75$1.75Lean buy
Constraint value -10%$32.88$2.88Lean buy
Base case$34$4Lean buy
Constraint value +10%$35.13$5.13Lean buy
Constraint value +20%$36.25$6.25Buy

Continue Analysis

Based on your results, these related decisions are available.

Resources

How this works

Comparing labor and material cost to a supplier's price is the naive make-vs-buy check, and it is wrong whenever the plant is constrained. Making a part in-house consumes hours on whatever resource is the real bottleneck, and those hours have a value: what they would have earned making the next most profitable thing instead. This engine adds that opportunity cost, priced at the constraint value you supply, to direct labor and material before comparing the fully loaded make cost to the supplier's buy price.

A one-time switching cost, such as supplier qualification or tooling transfer, is checked separately. Buying can be cheaper per unit and still be a bad near-term decision if the switching cost does not pay back within the volume and horizon entered, so the engine reports the per-unit verdict and the investment payback verdict as two distinct results.

Assumptions

  • Constraint value and unit costs are held constant across the volume and horizon modeled
  • One supplier quote is compared, not a multi-bid negotiation
  • Constraint hours freed by buying are assumed usable elsewhere at the same constraint value

Limitations

  • Does not model multi-supplier bidding or quality risk differences between sources
  • Does not model dual-sourcing or partial make/buy splits
  • Does not model supplier price changes with volume

Sources

Capital and cost-screening logic follows Blank and Tarquin, Engineering Economy (8th edition), the same source as the platform's other cost-decision engines. Constraint opportunity costing follows the Theory of Constraints throughput-accounting method already sourced in Contribution Margin per Constraint Hour.

Worked example

Making a part takes 1 hour of labor at $25/hour plus $5 of material and $1 of overhead, for $31 direct cost. If that hour also occupies the plant's bottleneck, and the bottleneck earns $30/hour on its next best use, the fully loaded make cost is $61. A supplier quote of $35 is clearly cheaper, a 43% saving per unit. At 1,000 units a year that is $26,000 in annual savings, comfortably covering even a real switching cost as long as the horizon is long enough: a $200,000 one-time switch would need more than a single year to pay back at that volume, which is exactly the kind of gap the separate investment check exists to catch.

Common use cases

  • Deciding whether to outsource a part when the shop is running near capacity
  • Checking whether a supplier's quote actually beats fully loaded make cost
  • Testing whether a switching investment (tooling, qualification) pays back fast enough
  • Freeing bottleneck capacity for higher-value work by moving a low-margin part to buy

Frequently asked

What is the constraint opportunity cost in this comparison?
If making the part in-house uses time on a constrained resource, that resource could have made something else; its opportunity cost is added to the make option so buying is not unfairly penalized.
Does a lower supplier price always mean buy?
Not necessarily; if in-house capacity is not actually constrained, the opportunity cost is low or zero, and make can still win even against a lower headline supplier price.
What if the part requires new equipment to make in-house?
Enter that as part of the investment case; a make decision that requires new capital has a materially different cost profile than one using existing idle capacity.
Does this consider supplier reliability or lead time risk?
No, this is a cost comparison only; supplier risk, quality history, and lead-time variability are real factors worth weighing alongside the cost result, not inside it.