Repair vs Replace Equipment
Compare the annualized cost of repairing versus replacing equipment, including downtime and maintenance cost, and see which option is cheaper per year.
- The repair cost is 33.3% of the replacement cost, well under the 50% rule threshold.
- Replacing is expected to reduce downtime by 25 hours/year.
- The added upfront cost of replacing pays back in about 9.1 years from the annual savings.
Sensitivity to downtime cost
| Scenario | EAC repair | EAC replace | Annual savings | Strategy |
|---|---|---|---|---|
| Downtime cost -20% | $11,466.67 | $7,800 | $3,666.67 | Replace |
| Downtime cost -10% | $12,066.67 | $8,025 | $4,041.67 | Replace |
| Base case | $12,666.67 | $8,250 | $4,416.67 | Replace |
| Downtime cost +10% | $13,266.67 | $8,475 | $4,791.67 | Replace |
| Downtime cost +20% | $13,866.67 | $8,700 | $5,166.67 | Replace |
Continue Analysis
Based on your results, these related decisions are available.
Resources
How this works
Repairing and replacing equipment rarely last the same number of years, so comparing their raw price tags is misleading. This engine converts each option's upfront cost into an equivalent annual cost using the capital recovery factor, then adds each option's own ongoing maintenance and downtime cost. The option with the lower annualized total is the economically preferred choice.
The classic "50% rule" (replace once repair cost exceeds half of replacement cost) is shown as a supplementary check, not the deciding factor, because it ignores remaining life, downtime, and ongoing maintenance cost. When the two disagree, the annualized-cost result governs.
Assumptions
- Each option's costs are treated as a level annual amount over its own expected life, with no cost escalation or inflation modeling
- Downtime hours and their cost per hour are constant year to year within each option
- The discount rate, when used, applies uniformly to both options
- Salvage value is realized once, at the time of replacement, and offsets the replacement capital cost
Limitations
- Does not model multiple future replacement cycles, only a single comparison cycle
- Does not model financing terms, taxes, or depreciation
- Does not model probability-weighted failure risk beyond the downtime-hour estimate provided
Sources
The equivalent annual cost method and capital recovery factor follow Blank and Tarquin, Engineering Economy (8th edition), and NIST Handbook 135, the Life-Cycle Costing Manual for the Federal Energy Management Program.
Worked example
A machine needs a $25,000 repair and would run another 2 years, with 120 hours of downtime expected per year at $250 an hour. A comparable new machine costs $90,000, lasts 12 years, and would cut annual downtime to 15 hours. Annualizing the repair's $25,000 over 2 years plus its downtime cost comes to about $42,500 a year. Annualizing the replacement's $90,000 over 12 years plus its lower downtime cost comes to about $11,250 a year, roughly $31,000 a year less than repairing. Even though the repair cost is only about a quarter of the replacement cost, well under the common 50% rule threshold, replacing is still the cheaper choice once the shorter remaining life and higher downtime of the repaired machine are both accounted for.
Common use cases
- Production machinery nearing the end of a repair-worthy life
- Forklifts and material handling equipment
- HVAC and facility mechanical systems
- Packaging and conveyance equipment
Frequently asked
- Why compare equivalent annual cost instead of upfront price?
- Repair and replacement have different cash timing and different useful lives; equivalent annual cost spreads each option's full cost, including downtime, over its own life so the two are actually comparable.
- Does this include the reliability improvement from replacing?
- Yes, a new asset's reliability improvement is a real input, since it changes expected downtime cost going forward, not just the purchase price difference.
- What if the current asset has been repaired multiple times already?
- Enter your current best estimate for this repair's cost and the asset's resulting reliability; repeated past repairs are relevant context for that estimate but are not tracked automatically.
- Does replacing always win when it changes capacity?
- No, a capacity change from replacing is priced as its own input; more capacity only helps the outcome if that capacity is actually needed and used.